Suspended ceiling work - Coordination on the installation process









1. The suspended ceiling work at Port Klang, Selangor for an engineering company incurred us extra cost in materials and labour / man-hours due to oversight on the coordination of the whole suspended ceiling construction process. Hence, this posting as reminder for future suspended ceiling work with the same conditions.

2. Sprinkle system alteration work, if there is any, is to go first before constructing the framework suspension system. Water that sprinkle out during the alteration work will spread to the suspension framework and cause it to rust. If there is already gypsum board partition wall being constructed, damage to the wall may happen if the board is not of water resistant type. 

3. Wiring and ducting work are to go first or before gypsum ceiling board is put up. The wiring work will be very much slowed down if it is done after the ceiling board is put up. That is apart form the high possibility if dirtying the ceiling board.

4. Hanger wire for light box cannot be drawn from the wire meant to hang the suspension system and ceiling board. The strength of the wire hanger suspension will be compromised if this is done, resulting in dropping or sagging ceiling in the future.